TeraWulf's HPC leases make up 83% of 3Q26 revenue

Google provides credit support for debt behind an approximately $19 billion Anthropic lease, but TeraWulf has not disclosed the support limit or the financing rate.

A corrugated-metal bitcoin-mining shed lined with exhaust fans stands beside the steel frames of three large data center buildings under construction, with cranes and an electrical substation nearby. AI-generated image

TeraWulf reported 3Q26 revenue of $76.2 million on 6 Nov 2026. High-performance computing (HPC) leases brought in $63.0 million of that, about 83% of the total. HPC lease revenue in 3Q25 was $7.2 million.

A company that has operated bitcoin-mining facilities now draws most of its revenue from HPC leasing, a shift made within a year. The next stage rests on an Anthropic lease the company puts at about $19 billion. Google's credit support sits behind the debt intended to finance it.

The questions that follow are when the money arrives, what Google is backing and when the buildings will be ready.

TeraWulf third-quarter revenue by segment

3Q25HPC lease revenue7,203
Digital asset revenue43,375
3Q26HPC lease revenue62,986
Digital asset revenue13,244
Source investors.terawulf.com · as of 2026-09-30 · unit: thousand US dollarsChart: made by LOGIT

A 20-year lease with Google credit support

TeraWulf announced a 20-year lease to Anthropic of about 401 MW of critical IT capacity, meaning power for IT equipment, at its Justified campus in Kentucky. The roughly $19 billion is contracted revenue across the full 20-year initial term, not money invested up front. The release does not say when rent payments begin or whether any rent is paid in advance.

TeraWulf announced on 4 Nov 2026 that it had signed credit support agreements with Google, which provides contractual credit support for debt the company expects to raise. Alphabet, Google's parent, has senior unsecured debt rated AA+ by S&P and Aa2 by Moody's. The company has not disclosed the limit of that support or the conditions that would trigger it.

TeraWulf said strong investment-grade credit support improves its ability to secure competitive project financing and long-term debt. "Cost of capital is fundamental to infrastructure development", Patrick Fleury, the chief financial officer, said in the release. The amount to be raised and the interest rate have not been disclosed.

The Fluor contract and each campus's remaining schedule

TeraWulf announced a definitive engineering, procurement and construction (EPC) agreement with Fluor covering three data centre buildings. Fluor has handled early engineering and pre-construction work since a limited notice to proceed in March 2026. The new agreement widens its scope to engineering, procurement, construction, testing and commissioning.

The contract uses a guaranteed maximum price (GMP), a form that caps what the client pays, and the company said the ceiling will be set as engineering and procurement progress. With labour availability becoming a growing constraint on large data centre development, the plan is to rely on Fluor's subcontractors and skilled workforce. The release gives neither the maximum price nor the date it will be fixed.

TeraWulf expects the facilities to be leased by Anthropic to become ready for service in phases from late 2027 through 2Q28. Contracted power at the Muskie campus has increased from 500 MW to 1,000 MW, an expansion subject to approval by state authorities. Delivery of the second 500 MW is expected in 2029.

From bitcoin mining sites to AI lease facilities

TeraWulf said it operates existing bitcoin-mining facilities at its Lake Mariner campus and is converting part of them to HPC use. It describes itself as an energy infrastructure company that pairs long-term access to power with contracted AI and HPC demand. Its model is to develop and operate the underlying infrastructure rather than invest in AI computing hardware.

The 3Q26 earnings release counted 102 MW of operating capacity at Lake Mariner. Another 336 MW is under construction across CB-4 and CB-5. CB-4 is due for phased delivery in 4Q26, and the target is for CB-5 to begin delivery in early 2027.

Cash, cash equivalents and restricted cash totalled about $2.4 billion at the end of 3Q26. The company announced that it raised its revolving credit commitments from $250 million to $400 million after the quarter closed. The sale of its 50.1% stake in the Abernathy joint venture brought in $250 million in cash during the quarter.

Net income rose to about $709.9 million in 3Q26, the company announced. That figure benefited from a non-cash change in the fair value of warrants, securities that give holders the right to buy shares at a set price. Adjusted earnings before interest, tax, depreciation and amortisation (EBITDA) was a loss of about $12.8 million.

TeraWulf's revenue mix has already shifted to leasing. The roughly $19 billion it cites is 20 years of contracted revenue from a campus that has yet to become ready for service.