South Korea opens consultation on AI data centre draft rules

The drafts specify when domestic operators would file notices for construction, operation and changes, and which projects outside the Seoul metropolitan area would qualify for a power grid assessment exemption.

A generic South Korean construction site with an unfinished concrete building, scaffolding, a tower crane, and excavated foundations. AI-generated image

South Korea’s Ministry of Science and ICT (MSIT) opened a public consultation on a draft enforcement decree and implementing rules under the Special Act on the Promotion of the AI Data Centre Industry. The ministry plans for both to take effect on 10 Mar 2027, when the Act comes into force.

The drafts set out when domestic operators would file notices and which projects could qualify for an exemption from an assessment of their impact on the power grid. Deputy Prime Minister and Science and ICT Minister Bae Kyung-hoon said on Policy Briefing, the Korean government’s news portal, that the rules would help operators determine which facilities qualify for support under the Act and what benefits they could receive.

The drafts also cover facilities that host AI server racks owned or managed by other operators. These facilities provide space equipped with power, communications and cooling systems for installing and operating the racks.

Filing deadlines for operators

Under MSIT’s drafts, operators would file a construction notice before work begins and an operation notice 30 days before operations start. They would file a change notice within 30 days of the event that requires it.

MSIT said operators would also have to set and report a construction start date within one year of filing their construction notice. The requirement is intended to prevent operators from securing benefits such as a grid assessment exemption by filing a notice and leaving construction unstarted.

Grid assessment exemptions outside the Seoul metropolitan area

Under MSIT’s drafts, the exemption would apply to new or expanded AI data centres outside the Seoul metropolitan area, as well as those established there by converting existing facilities. Eligible data centres would need a contracted power capacity of 50 MW or less.

MSIT also plans to give priority in grid assessments to facilities eligible to have their permits processed together. It proposed waiving the non-technical part of the assessment for facilities in designated special zones. The ministry has yet to disclose when either measure would take effect.

Rulemaking after the public hearing

MSIT plans to hold a public hearing on the ninth of next month at Nuritkum Square in Seoul’s Mapo district. It will accept comments by email or post until 30 Dec 2026.

The filing procedures and grid assessment exemption criteria remain provisional. MSIT plans to take the drafts through legal review after the comment period closes.