Korea proposes grid review exemptions for AI data centres
Korea proposes a contracted power threshold for exemptions outside the Seoul metropolitan area and plans to give large projects priority in grid reviews.

South Korea’s government published a draft enforcement decree under its special law on AI data centres on 20 Nov 2026, proposing exemptions from power grid impact assessments for centres outside the Seoul metropolitan area, according to Korean news outlet Digital Today. The report gave no effective date.
The government said the changes to assessments, which examine how a project would affect the power grid, are intended to speed up data centre construction.
Digital Today reported that the government set out two measures: exemptions based on where centres are built and priority processing for large projects that undergo assessment.
Grid assessment exemptions by location
According to Digital Today, the draft decree sets the exemption threshold for centres outside the Seoul metropolitan area at 50 MW or less of contracted power, the capacity agreed with the electricity supplier.
In special zones for AI data centres, the government said the exemption it plans covers the non-technical parts of the assessment.
Priority assessments for large projects
The Ministry of Science and ICT (MSIT), Korea’s science and technology ministry, and the Ministry of Climate, Energy and Environment, which oversees those policy areas, said they plan to give large projects priority in the assessment process.
The priority process remains a plan. The government’s proposal, as reported by Digital Today, gives no project-size threshold for eligibility.