04 / Policy · Policy
President Lee inspects SK AI data centre construction site
The site manager reported that construction was 71% complete, and Korea’s presidential office said operations are due to begin in late 2027.
Key points
- 01Blue House publication of the inspection briefing on 21 Nov 2026
- 02Deputy spokesperson’s written briefing on the Ulsan construction site
- 03Backup power during the switch to emergency generators
The Blue House, South Korea’s presidential office, published a written briefing by deputy spokesperson An Gwi-ryeong on 21 Nov 2026 about President Lee Jae-myung’s inspection of the SK AI data centre construction site in Ulsan. It said the data centre is scheduled to begin operating in late 2027.
Construction progress. The briefing identified the site as the Mipo National Industrial Complex in Ulsan’s Nam district. Kim Jong-yeon, the site manager for SK ecoplant, a South Korean construction company, reported that construction was 71% complete.
Project milestones. According to the Blue House, Lee attended the launch ceremony for the Ulsan AI data centre on his first regional engagement after taking office in June last year. During this visit, he received an update on the installation of major equipment and inspected the construction work.
Backup power. According to the briefing, Kim explained that an uninterruptible power supply can keep the facility powered for about three seconds while the emergency generators start up after an outage.
Specialist workers. The Blue House said Lee told officials that the government would consider ways to secure the specialist workers needed to build advanced facilities.
The briefing did not disclose any specific measures to secure those workers.