04 / Policy · Analysis
Korea proposes AI data centre power assessment exemption
Draft rules use contracted power to define which AI data centres outside the capital region qualify for an exemption and clarify how facilities qualify for special provisions.

The Ministry of Science and ICT (MSIT), Korea’s science and ICT ministry, published draft implementing regulations and rules for public comment on 20 Nov 2026, according to Korean technology news outlet ETNews. The drafts implement the Special Act on the Promotion of the AI Data Centre Industry and propose a power grid impact assessment exemption for eligible projects outside the capital region.
According to ETNews, eligibility for the proposed exemption turns on contracted power, the amount of power specified in a facility’s electricity supply contract.
ETNews reported that the same requirement would apply when an existing facility outside the capital region is converted into an AI data centre.
Contracted power and exemption eligibility
According to ETNews, new builds, expansions and conversions outside the capital region would qualify for the proposed exemption if their contracted power is 50 MW or less.
ETNews reported that facilities at the ceiling would also qualify.
Recognition criteria for special provisions
ETNews reported that the government also clarified the criteria for recognising AI data centres eligible for special provisions under the act.
According to ETNews, those criteria are part of the draft rules published for public comment ahead of implementation.