Korea plans grid review waivers for regional AI data centres

Korea’s draft rules set out which AI data centres would qualify for a power grid assessment exemption and how centres would be recognised as eligible for support under the special law.

Two engineers seen from behind practice network security configuration beside server racks in an AI infrastructure training lab. AI-generated image

Korea’s Ministry of Science and ICT (MSIT), which oversees science and technology policy, said it would open public consultation on 20 Nov 2026 on draft rules that would exempt AI data centres outside the Seoul capital area from power grid assessments if their contracted power is 50 MW or less, ZDNet Korea reported. The ministry plans for the rules to take effect alongside the special law on 10 Mar 2027.

According to the report, the drafts specify which centres would qualify for support under the law and which would be exempt from assessment when the law takes effect.

Eligibility for the exemption depends on the centre’s location and contracted power, ZDNet Korea reported. The assessment examines how a facility would affect the power grid.

Grid assessment exemption criteria

Under the draft rules reported by ZDNet Korea, the exemption covers AI data centres built outside the Seoul capital area with contracted power of 50 MW or less.

The drafts also set criteria for recognising centres as eligible for support under the special law and spell out how operators’ permits and approvals would be processed together, according to the report.

Adoption of the implementing rules

According to ZDNet Korea, the Special Act on the Promotion of the Artificial Intelligence Data Centre Industry was promulgated on 9 Jun 2026. The consultation covers the enforcement decree and enforcement rules that implement the Act.

MSIT said the consultation would run through 30 Dec 2026, ZDNet Korea reported. The grid assessment exemption criteria are part of the consultation draft and have yet to be finalised.